Network Planning Analysis Using CPM and PERT Methods on Optimization of Time and Cost
DOI:
10.33395/sinkron.v8i1.11961Keywords:
Keywords: Network Planning, Optimal Duration, CPM and PERT, Crashing MethodAbstract
The shipbuilding industry is the most important industry to support sea transportation in the context of maritime development. As a company engaged in shipping, the function of the shipyard is as a place for shipbuilding, ship repair, and ship maintenance. One of the activities carried out by PT. DNC as a shipyard company is to repair TK Aek Sigala-gala. Ship repair is a process of repairing or replacing ship materials that cannot be used to avoid risks that occur in the sea when the ship sails. In the implementation of project activities, the company must understand the right network so that there are no problems scheduling, planning and controlling project activities. This study aims to solve the problems faced by the company, is the delay in completion time. The data used is secondary data related to the sequence and relationship of activities, execution time, and cost budget plan (RAB). This study uses CPM and PERT methods to determine the optimal turn around time using critical path and probability concepts. The results of the CPM and PERT methods are activities on the critical path with an optimal duration of 98 days. The crashing method is to reduce the duration to 72 days with savings of Rp. 16,351,708. if the project implementer does not crash, the penalty that must be paid is Rp. 3,072,963,905.
Downloads
References
Abraham, I. J., & Ridwan, A. (n.d.). Percepatan Waktu Pelaksanaan Pembangunan Gedung Rumah Sakit Aisyiyah Kabupaten Ponorogo Menggunakan Metode PERT (Program Evaluation and Review Technique). https://doi.org/10.30737/jurmateks
Anenda, L. (2020). Analisis network planning pada proyek konstruksi jalan oleh CV. X menggunakan metode Program Evaluation Review Technique (PERT)-Critical Path Method (CPM). http://digilib.uinsby.ac.id/42087/
Deni Prawira. (2020). Penerapan Metode Critical Path Method (CPM) Pada Network Planning Dalam Efisiensi Waktu dan Biaya Proyek Pembangunan Rumah Minimalis (Studi Kasus: Property Group Medan). Jurnal Sistem Komputer Dan Informatika …, 2(1), 80–89. https://doi.org/10.30865/jurikom.v7i4.2266
Haryanto, B., & Jamal, M. (2021). Perbandingan Penjadwalan Proyek Dengan Metode PDM (Precedence Diagram Method) & CPM (Critical Path Method) (Studi Kasus: Lanjutan Pembangunan Proyek Gedung SD Islamic Center Samarinda). Teknologi Sipil, 5(2), 17–25.
John M. Nicholas, H. S. (2008). Project Management for Business, engineering, and Technology (3rd ed.). Elsevier. http://digilib.uinsby.ac.id/42087/
Lokajaya, I. N. (2019). Analisis Pengendalian Waktu Dan Biaya Pada Proyek Peningkatan Jalan Dengan Metode Cpm Dan Pert. Heuristic, 16(2), 104–125. https://doi.org/10.30996/he.v16i2.2970
Luhur P, H. A., Hadi, E. S., & Amiruddin, W. (2017). Analisis Network Planning Reparasi Kapal SPB TITAN 70 dengan Metode Critical Path Method. Jurnal Teknik Perkapalan, 5(2), 421–430.
Meflinda, A., & Mahyarni. (2011). Riset Operasi.pdf (p. 120). http://ejournal.uin-suska.ac.id
Rusdiansyah, R., Handrianto, Y., Supendar, H., & Tuslaela, T. (2022). Application of the Hungarian Method and Software Quality Management (QM) Testing in Determining Optimal Wage Costs at OneTop Frozen Food Stores. SinkrOn, 7(2), 376–383. https://doi.org/10.33395/sinkron.v7i2.11330
Saputra, L. I., Budiarto, U., & Jokosisworo, S. (2017). Studi Penjadwalan Ulang, Produktivitas, Dan Alokasi Sumber Daya Manusia Pada Pekerjaan Reparasi Kapal MT. Asumi XXVI Dengan Network Planning Dan Critical Path Method. Teknik Perkapalan, 5(2), 421–430.
Sari, R. P., Jayadi, O., & Nugraha, L. T. (2018). Optimalisasi Proses Manufaktur dalam Pembuatan Pipa Union dengan Menggunakan Metode Hungarian dan PERT/CPM. JIEMS (Journal of Industrial Engineering and Management Systems), 11(1), 1–6. https://doi.org/10.30813/jiems.v11i1.1010
Sitorus, S. P., Hasibuan, E. R., & Rohani, R. (2022). Analysis performance of content delivery network by used Rateless Code method. Sinkron, 7(4), 2348–2359. https://doi.org/10.33395/sinkron.v7i4.11651
Soeharto, I. (1999). Manajemen Proyek (Dari Konseptual Sampai Operasional). In Erlangga (Kedua). Erlangga. https://doi.org/10.3938/jkps.60.674
Tarigan, A. J. M., Mardiningsih, M., & Suwilo, S. (2022). The search for alternative algorithms of the iteration method on a system of linear equation. Sinkron, 7(4), 2124–2424. https://doi.org/10.33395/sinkron.v7i4.11817
Widiarina, W., Mariskhana, K., & Sintawati, I. D. (2022). Assignment of Motor Mechanics at the Tire Palace Using the Hungarian Method and Testing Software Quality Management (QM). SinkrOn, 7(2), 413–420. https://doi.org/10.33395/sinkron.v7i2.11336
Yuliarty, P., Novia, N. S., & Anggraini, R. (2021). Construction Service Project Scheduling Analysis Using Critical Path Method (CPM), Project Evaluation and Review Technique (PERT). International Journal of Innovative Science and Research Technology, 6(2), 2019–2022. www.ijisrt.com
Downloads
How to Cite
Issue
Section
License
Copyright (c) 2023 Surayya Aulia, Hendra Cipta
This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.